MPs slam MoD handling of IT project
By Miya Knights,
The Public Accounts Committee (PAC) has made damning criticisms of the Ministry of Defence’s (MoD) handling of a £7-billion project to upgrade its computers.
A PAC report published today said the Defence Information Infrastructure (DII) project, established in 2005, had been “badly planned”. The report called for “rapid improvement” if cost-saving benefits were to be fully achieved.
The contract to design, install and run the DII project was awarded to the ATLAS consortium. The programme aimed to provide 150,000 terminals, supporting 300,000 MoD users at more than 2,000 sites by 2015, with additional capability on deployed operations and Royal Navy ships.
But the PAC report said the project had been beset by delays, leaving users reliant on out-of-date systems and the MoD exposed to increased risk of IT systems failure.
PAC chairman Edward Leigh said in a statement that the project had been “badly planned in important respects”.
The report said: “The main causes of delay were the programme’s over-optimistic assumptions about the condition of the buildings into which DII would be fitted, and the consequent selection of an inappropriate and unresponsive methodology for installing terminals.”
As a result, only 45,600 terminals were in place by the end of September 2008, when 62,800 terminals should have been installed by the end of July 2007. And, the cost of the project had risen by £182 million.
The report also criticised the ATLAS consortium's lead provider, EDS, for underestimating the complexity of the software it had to develop.
“For over two years, it was unable to deliver a system that could safely handle secret material,” Leigh added.
He also said that the contractor’s track record on government IT project delivery “has not been exemplary,” just as the MoD had been unable to adequately protect sensitive data, following a number of recent high-profile data loss incidents.
The report did say the department had been able to protect the project’s benefits, which amount to an estimated £1.5 billion, and that roll-out performance had improved recently, with new software tested and 3,400 terminals rolled out on average each month.
But it added: “Rapid improvement to 4,300 terminals a month will be needed if the department’s latest deadlines are to be met.”
The PAC report largely echoed the findings of an equally damning National Audit Office report published last July.
You may also like...
Sponsored Links
advertisement
You may also like...
Latest Public Sector Analysis & Insight
Striving to solve the security skills crisis
The Cyber Security Challenge is doing a fine job, but flat registration growth and weak Government funding are cause for concern, Tom Brewster discovers.
- 2011: The year in news
- Are the cookie laws crumbling already?
- UK rural broadband: too little, and too late
- How the Data Protection Act's death will punish the UK economy
- Education: glad to be a geek
- Plugging public sector data leaks
- Going for Gold - IT at the London Olympics
- Fujitsu: out to steal HP market share
- What will Windows Mango mean for business?
Latest Public Sector Reviews
HTC Flyer review: First Look
- HP TouchPad review: First Look
- RIM BlackBerry PlayBook review - First Look
- MWC 2011: Acer Iconia A100 and A500 reviews – first look videos
- MWC 2011: HP TouchPad review - first look video
- MWC 2011: RIM BlackBerry PlayBook review - first look video
- MWC 2011: HP Pre3 review - first look video
- MWC 2011: Motorola Pro review - first look video
- MWC 2011: HTC Flyer tablet review - first look video
- MWC 2011: Samsung Galaxy Tab 10.1 review – first look video
advertisement
Most popular
- Ubuntu vs. Windows 7 on the business desktop
- York researchers heat storage to speed up data
- BlackBerry Bold 9790 review
- OneNote hits Google?s Android
- O2 trials Olympic-scale remote working
- Will someone rid me of these troublesome Macs?
- Lenovo beats expectations again
- Who to trust after the VeriSign hack?
- Google to promise fairness after Motorola buy
- Report: Google cloud storage coming soon
Latest News Videos in Public Sector
Q&A: David Elton, PA Consulting Group
CIOs are increasingly influential, but have to juggle "dual roles", study finds.
Register for IT PRO
You'll get exclusive member benefits including free whitepapers, downloads, Webinars and weekly newsletters full of the latest IT PRO news, reviews, insight and expertise.